    Design Details: Order

    In a make-to-order environment, an item is purchased or produced to exclusively cover a specific demand. Typically it relates to A-items, and the motivation for choosing the order reordering policy can be that the demand is infrequent, the lead-time is insignificant, or the required attributes vary.

    The program creates an order-to-order link, which acts as a preliminary connection between the supply, a supply order or inventory, and the demand that it is going to fulfill.

    Apart from using the Order policy, the order-to-order link can be applied during planning in the following ways:

    • When using the Make-to-Order manufacturing policy to create multi-level or project type production orders (producing needed components on the same production order).
    • When using the Sales Order Planning feature to create a production order from a sales order.

    Even if a manufacturing company considers itself as a make-to-order environment, it might be best to use a Lot-for-Lot reordering policy if the items are pure standard without variation in attributes. As a result, the system will use unplanned inventory and only accumulates sales orders with the same shipment date or within a defined time bucket.

    Order-to-Order Links and Past Due Dates

    Unlike most supply-demand sets, linked orders with due dates before the planning starting date are fully planned for by the system. The business reason for this exception is that specific demand-supply sets must be synchronized through to execution. For more information about the frozen zone that applies to most demand-supply types, see Design Details: Dealing with Orders Before the Planning Starting Date.

    See Also

    Design Details: Reordering Policies
    Design Details: Planning Parameters
    Design Details: Handling Reordering Policies
    Design Details: Supply Planning

    Back to top Copyright © 2020 Aptean
    JustFood Spring 2019 Service Pack 1